(Page 1) Early April 2005: In the
Beginning...
(Page 1) April/May 2005: Preliminaries
Week of May 15th,
Workday with
Ananda Seattle members
Week of May 22nd:
Preparation
for Memorial Day Work Week
(Page 3) May 26-30th: Work Week with
Ananda members nationwide
(Page 4) Week of May 29th: Follow-up
(Page 5) Continued Work, June 5th-24th
(Page 6) Installation of Lotus Window, July 7th
(Page 7) Insulation, Sheetrock, and Construction of Arches, July 20-23
(Page 8) Construction of Exterior Rooflines, July 24-30
(Page 9) Continued Rooflines plus August 13th Workday
(Page 10) Exterior Detailing & Venting,
August 21-28
(Page 11) More Exterior Detailing, Walkway,
and Interior Altar, August 29-Sept 9
(Page 12) Exterior Stucco, Oct 1 Workday
(Page 13) Interior Sheetrock & Painting,
Stone Work, Door Installation, October
(Page 14) EMD's and Carpet
(Page 15) Altar Pictures and More
Week of May 15th, Workday with Guests from Ananda
Seattle
This week we got our permits from the City of Beaverton so construction
could move ahead full-steam. On the 21st we welcomes guests from Ananda in
Seattle for a workday as you'll see below. One item not seen in these
pictures was the installation of structural steel on the inside of the
sanctuary to replace the brick columns on the exterior.
Removing the glass from the East sanctuary wall


Opening the ceiling in the foyer


Repairs to the roof in the children's play area

Preparation and pouring of the first section of the new entryway
(the kids in our Living Wisdom School helped out too!)




Removal of exterior brick columns