Mandir Remodeling Project Status Page 8
(Page 1) Early April 2005: In the
Beginning...
(Page 1) April/May 2005: Preliminaries
(Page 2) Week of May 15th, Workday with
Ananda Seattle members
(Page 2) Week of May 22nd: Preparation
for Memorial Day Work Week
(Page 3) May 26-30th: Work Week with
Ananda members nationwide
(Page 4) Week of May 29th: Follow-up
(Page 5) Continued Work, June 5th-24th
(Page 6)
Installation of Lotus Window, July 7th
(Page 7) Insulation, Sheetrock, and Construction of Arches, July 20-23
Construction of Exterior
Rooflines, July 24-30
(Page 9) Continued Rooflines plus August 13th Workday
(Page 10) Exterior Detailing & Venting,
August 21-28
(Page 11) More Exterior Detailing, Walkway, and Interior Altar, August
29-Sept 9
(Page 12) Exterior Stucco, Oct 1 Workday
(Page 13) Interior Sheetrock & Painting,
Stone Work, Door Installation, October
(Page 14) EMD's and Carpet
(Page 15) Altar Pictures and More
Construction of Exterior Rooflines, July 24-30
Thanks to the timely help of
Jim McGee and Gregory Sagmeister, we made our way through one of the most
technically difficult parts of the projects, namely the curved roof lines
around the entryway and along the facade. This now places us in a position
to complete the roofing over the entryway, making it watertight, which in
turn allows us to move forward on interior finish work.
Meanwhile, more electrical work has also been happening.
Work beginning; you can see the special curved rafters taking shape:

The roof line going into place

Hey David! Look toward the camera!

The facade of the mandir on July 31st; closer and closer to the design
drawings...